OAHU TRANSPORTATION IMPROVEMENT PROGRAM, FYS 2004-2006 AS OF AMENDMENT #13 Project Status Report for Federally-Funded Projects in Federal Fiscal Year 2005 As of September 30, 2005 STATE OF HAWAII PROJECTS |
||||||
Project |
Phase |
ESTIMATED in FY 2005 (x $1,000) |
TEA-21 FUNDING CATEGORY |
OBLIGATED (Yes/No) |
STATUS |
|
FEDERAL HIGHWAY ADMINISTRATION |
||||||
S2 |
Farrington Highway , Bridge Replacement, Makaha Bridges #3 and #3A |
ROW |
1,300 |
Bridge On-System |
No |
TIP Am #13 split up ROW into 2 parts, prelim in FY ‘05 and Acq. in FY ‘06. Prelim ROW was obligated in FY ‘04. |
S6
|
Fort Barrette Road Widening, Farrington Highway to Franklin D. Roosevelt Avenue |
ROW
|
170
|
Minimum Guarantee
|
Yes |
|
S7 |
Fort Weaver Road Widening, Vicinity of Aawa Street to Geiger Road |
CON |
45,800 |
Congestion Mitigation and Air Quality |
Yes
|
|
S17
|
Interstate Route H-1, Guardrail and Shoulder Improvements, Waikele Bridge to Airport Interchange |
CON
|
4,300
|
Interstate Maintenance
|
No. |
Section 106 could not be processed in time. Will be proposed to be added to FY ’06. |
S18 |
Interstate Route H-1, Highway Lighting Improvements, Vicinity of Kaimakani Overpass to Vicinity of Gulick Avenue |
ESD |
600 |
Interstate Maintenance |
Yes |
|
S22
|
Interstate Route H-1, Rehabilitation, Kaahumanu Street to Kaimakani Street Resurface existing roadway. |
CON
|
15,000
|
Interstate Maintenance
|
Yes |
|
S27 |
Interstate Route H-1, Waiawa Interchange, Westbound, Additional Westbound Lane Construct an additional lane through the Waiawa Interchange, beginning in the vicinity of the Pearl City Viaduct and ending at the Paiwa Interchange. |
DES |
2,500 |
National Highway System |
No |
Local funds only. In FY ‘07 of FYs ‘06-‘08 STIP. |
S28 |
Interstate Route H-1, Waiawa Interchange, Westbound, Waipahu Off-Ramp Improvements Widen the Waipahu off-ramp from one to two lanes. |
DES |
3,000 |
Interstate Maintenance |
No |
Local funds only. In FY ‘07 of FYs ‘06-‘08 STIP. |
S29 |
Interstate Route H-1, Ward Avenue On-Ramp to University Interchange Improve eastbound traffic flow from the Ward Avenue on-ramp to the University interchange. |
PLN |
1,500 |
National Highway System |
No |
Local funds only. No PM. |
S34 |
James Campbell National Wildlife Refuge To be administered by the U.S. Fish and Wildlife Service. |
DES |
30 |
Public Lands Discretionary |
No |
Dropped. |
S36 |
Kalanianaole Highway , Bridge Replacement, Inoaole Stream Bridge (Near Bellows Air Force Station, Waimanalo). Replace existing bridge with a larger bridge. Project will include improvements to the roadway approaches, detour road, and utility relocations. |
ROW |
525 |
National Highway System |
No |
Deferred. Proposed for addition to FY ’06. |
S38 |
Kalanianaole Highway Improvements, Olomana Golf Course to Waimanalo Beach Park Improvements include the construction of turning lanes, sidewalks, wheelchair ramps, bike paths or bike lanes, traffic signal upgrades, utility relocations, and drainage improvements. |
DES |
625 |
National Highway System |
No |
Deferred. In FY ’06. |
S40 |
Kalanianaole Highway , Intersection Improvements at Hanauma Bay Construction of left-turn lane into Hanauma Bay. |
CON |
2,000 |
National Highway System |
No |
Deferred. Proposed for addition to FY ’06. |
S45 |
Kamehameha Highway , Bridge Replacement, Kaluanui Stream Bridge (Hauula, near Sacred Falls State Park) Replace the existing bridge with a concrete structure that meets current design standards. The new structure will accommodate sidewalks and bridge railings. |
ROW |
700 |
Bridge On-System |
Yes |
|
S52 |
Kamehameha Highway , Bridge Replacement, Waiahole Bridge |
ROW CON |
640 6,055 |
Bridge On-System Bridge On-System |
No |
Deferred. Proposed for addition to FY ’06. |
S53 |
Kamehameha Highway , Highway Lighting Improvements, MP 20.7 to MP 23.8 |
DES |
400 |
National Highway System |
Yes |
Obligated with S18 and S69. |
S54 |
Kamehameha Highway Improvements, Waipahu Street to Ka Uka Boulevard |
ROW |
150 |
National Highway System |
Yes |
|
S56 |
Kamehameha Highway , Rehabilitation of Laieloa Stream Bridge |
DES |
725 |
Bridge On-System |
Yes |
|
S59 |
Kamehameha Highway , Rehabilitation of Waipilopilo Stream Bridge |
DES |
590 |
Bridge On-System |
Yes |
|
S61 |
Kamehameha Highway , Rockfall Protection at Waimea Bay, MP 5.4 to MP 5.52 |
DES |
1,000 |
National Highway System |
No |
Local funds only. No PM. |
S64 |
Kamehameha Highway Widening, Lanikuhana Avenue to Ka Uka Boulevard |
PLN |
1,500 |
National Highway System |
Yes |
|
S66 |
Leeward Community College (LCC) Second Access Improvements |
DES ROW |
1,000 500 |
Local Local |
No |
Deferred to FY ’07. |
S68 |
Moanalua Freeway and Interstate H-2 Freeway, Guardrail and Shoulder Improvements |
DES |
250 |
Interstate Maintenance |
Yes |
|
S69 |
Moanalua Freeway, Highway Lighting Improvements MP 0 to MP 0.73 and MP 1.12 to MP 4.09 |
DES |
100 |
Interstate Maintenance |
Yes |
Obligated with S18 & S53. |
S70 |
Moanalua Freeway, Seismic Retrofit, Puuloa Interchange, Puuloa Separation |
DES |
1,230 |
Bridge On-System |
Yes |
|
S74 |
North/South Road , Kapolei Parkway to Vicinity of Interstate Route H-1 |
ROW CON CON |
500 6,750 13,250 |
STP Flexible STP Flexible High Priority |
Yes |
|
S83 |
Oahu Railway and Land (OR&L), Repair Tracks, Fort Weaver Road to Kahe Point |
EQP |
50 |
STP Enhancement |
No |
Environmental docs not ready. May go all local funds. |
S76 |
Sand Island Tunnel - Kalihi Channel |
PLN |
2,000 |
National Highway System |
No |
This project was dropped by Harbors Division. |
S80 |
Vanpool Program |
OPER OPER
|
800 1,040 |
Congestion Mitigation and Air Quality FHWA funds transferred from FTA Sec. 5307 (C17 below) |
Yes |
|
S84
|
Elderly & Persons w/ Disabilities Program Vehicle Acquisition for Urban Areas |
EQP
|
415
|
FTA §5310
|
|
|
OAHU TRANSPORTATION IMPROVEMENT PROGRAM, FYS 2004-2006 AS OF AMENDMENT #13
Project Status Report for Federally-Funded Projects in Federal Fiscal Year 2005 As of September 30, 2005
CITY AND COUNTY OF HONOLULU PROJECTS |
||||||
Project |
Phase |
ESTIMATED in FY 2005 (x $1,000) |
TEA-21 FUNDING CATEGORY |
OBLIGATED (Yes/No) |
STATUS |
|
FEDERAL HIGHWAY ADMINISTRATION |
||||||
C1 |
Bridge Inspection and Appraisal Program |
PLN |
350 |
Bridge Off-System |
No |
Programming documents for planning funds have not been submitted to the State. Will not program funds. |
C2 |
Computerized Traffic Control System Phase 6 |
|
|
|
|
Ph 6 Construction – Programming of funds completed on 9/14/05. STP-001(23) PH 9 Design – Programming of funds completed on 8/8/05. STP-001 (30) Ph 10 Design- Programming documents have not been submitted to the State. Will not program funds. |
C3 |
Honolulu Traffic Control Center Operations |
OPER |
300 |
Congestion Mitigation and Air Quality |
Yes |
Programming of funds completed on 8/2/05. CMAQ-001(31) |
C18 |
Kamokila Boulevard Extension |
DES CON |
400 3,900 |
STP Flexible STP Flexible |
Not Applicable |
Procedure of design consultant using local funds is in progress. |
C19 |
Kapolei Parkway , Unit 1 |
PLN DES |
350 450 |
STP Flexible STP Flexible |
No |
Programming documents for planning and design funds will not be submitted to the State. Design will be done using local funds only. |
C21 |
Kapolei Parkway , Unit 2
|
PLN |
500 |
Local |
Not Applicable |
No action has been taken on this project. The City will not utilize the local funds for this project. |
C6 |
Salt Lake Boulevard , Halawa Stream Bridge Rehabilitation |
CON |
750 |
Bridge Off-System |
Yes |
Programming of funds completed on 6/8/05.
|
C8 |
Seismic Bridge Retrofit, Various County Bridges |
DES CON |
350 600 |
Bridge Off-System Bridge Off-System |
No |
Programming documents have not been sent to the State. Will not program funds. |
C9 |
Traffic Signals at Various Intersections |
CON DES |
2,000 200 |
STP Flexible STP Flexible |
No Yes |
Phase 7 Construction - Programming documents have been sent to the State on 8/5/05. Phase 9 Construction – Programming of funds was completed on 4/28/05. |
FEDERAL TRANSIT ADMINISTRATION |
||||||
C11 |
Bus and Handi-Van Acquisition Program Purchase replacement buses and paratransit buses. |
EQP EQP |
23,000 2,400 |
Section 5309 Bus Capital Sec 5309 Fixed Guideway Modernization |
|
Initiated procurements. § 5307: HI90x022-01 awarded 6/30/05 |
C13 |
Middle Street Intermodal Center |
DES CON |
600 9,816 |
Section 5309 Bus Capital Section 5309 Bus Capital |
No Yes |
Design – Grant application did not request funds. Construction – Conditional award issued (HI030035) except for approx. $1.8M identified as contingency project in application. |
C16 |
Preventive Maintenance |
OPER OPER |
26,625 9,000 |
Section 5307 Urbanized Area Formula |
Yes |
Draw downs completed. |
C17 |
Transfer to FHWA for Vanpool |
OPER |
2,210 |
Section 5307 Urbanized Area Formula |
Yes – FFY 2004 funds No – FFY 2005 funds |
FTA approved transfer on 1/12/05. DTS reviewing internal ADA investment certification prior to requesting OMPO certification. |
C14 |
Wahiawa Transit Center |
ROW |
727 |
Local |
Not applicable |
ROW acquisition not required. |
C15 |
Waianae Transit Center |
ROW CON CON |
|
Local |
Yes |
§5309: HI030035 Conditional award issued. |